TxDOT update for the Week of June 27

txdotPress release

TxDOT (Athens) Maintenance, along with the Special Jobs Crew, continues mill and inlay operations working on Business (BU) 19 from the Downtown Square going north to Loop 7. Work then moves to BU 31 from US 175 westward to Loop 7. Expect lane closures at each location with flaggers providing traffic control.

Ongoing Henderson County construction projects updates:

FM 317 Repair Project

  • Limits: .At Athens Fish and Game Lake Dam
  • Contractor: Fritcher Construction
  • Cost: $446,216.00
  • Anticipated Completion Date: Late Summer 2016

Work to repair this roadway started in May and continues on schedule. The road closed in March 2015 due to a flood-related washout about three miles east of SH 31. Repairs should take about three months to complete, weather permitting. The plans for the permanent repairs have been coordinated with the Corp of Engineers and the Texas Commission on Environmental Quality (TCEQ).

US 175 Widening Project (Phase I)

  • Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
  • Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
  • Cost: $39.2 million
  • Anticipated Completion Date: November 2018

The eastern portion of Loop 60 is closed through July for construction of the new westbound mainlanes on this project that expands US 175 from two lanes to a four-lane divided with a depressed median. Drivers should expect one lane carrying two-way traffic throughout the project limits as well as occasional day time lane closures. Drivers on adjacent county roads and FM 804 should anticipate a change in traffic flow due to the detour now requiring two-way traffic on US 175. Dirt and drainage work around Loop 60E in Larue to near Baxter is ongoing. The speed limit in the construction zone has been set at 55 mph so slow down because traffic fines double when workers are present. Phase I construction started April 6, 2015.

US 175 Widening Project (Phase II)

  • Limits: 1.1 miles east of Loop 60B to 0.85 mile east of FM 315
  • Contractor: Sundt Construction, Inc., of San Antonio
  • Cost: $37.8 million
  • Anticipated Completion Date: 2018

The contractor continues dirt work around FM 315 south of Poynor as well as drainage work throughout the project. As part of the new highway construction, a short stretch of CR 4401 has been permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 will remain open and can be accessed from CR 4345/Camp Road.

This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.

US 175 Widening Project (Phase III)

  • Limits: 0.85 miles east of FM 315 in Poynor, southeast to .5 miles NW of SH 155 at Frankston
  • Contractor: A.L. Helmcamp, Inc.
  • Cost: $27.6 million

This project to expand US 175 from two lanes to a four-lane divided highway with a depressed median is underway. The contractor on Monday plans to begin placing concrete traffic barriers from the Frankston city limits to Oak Ridge Street in preparation of shifting traffic to the new detour pavement between County Road (CR) 303 and Oak Ridge Street. Other ongoing work includes clearing right of way from CR 4236 to the Poynor city limits, and installing a drainage culvert west of CR 303. Expect daily lane closures.

FM 315/FM 1616 Widening Project

  • Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
  • Contractor: Big Creek Construction, LTD, of Hewitt, Texas
  • Cost: $3.07 million
  • Anticipated Completion Date: Late Summer 2016

The construction widening project is ongoing with work to extend the cross structures. Drivers should anticipate one-way traffic throughout the project limits with daily lane closures. FM 1616 is expected to be completed this summer. Final work is being performed on FM 315.

SH 31 Bridge Painting Project – Westbound at Trinity River/Eastbound at Cedar Creek

  • Limits: From just east of Cedar Creek to just west of the Trinity River
  • Contractor: Olympus Painting Contractors Inc., of Clearwater, Florida
  • Cost: $2.3 million
  • Anticipated Completion Date: Summer 2016

Westbound traffic returns to the left travel lane starting Monday (June 27). The contractor continues work including sealing the bridge deck joint and applying permanent striping. Expect minor delays and lane closures. Daily closures of the eastbound lane at the Cedar Creek Bridge can also be expected as crack repair starts on the bridge deck.